Richmond Terminal Station

D Form Civil were engaged by Multiworks to complete the formwork package of the 220kV Cable Culvert at the Richmond Terminal Station Upgrade project. Being our first contract works within the live electrical substation sector, this project was key to prove the capabilities of our teams within these High-Risk work environments. The first package included forming approx. 50lm of 2m high walls which would eventually house connecting 220kV Cables from the GIS Building to a Transformer.

Upon successful completion of the 220kV Culvert, D Form Civil were then engaged to form the basement walls, columns, and suspended slab for the 66kV GIS Building within the station. The building was on the critical path for the client, and as such the works needed to be well planned to ensure that the timeframes were met. Through consultation with the client, the methodology was revised which allowed 75lm of 3.2m high walls to be formed and poured within 5 days. This allowed the remaining works to be completed ahead of schedule.

Get in touch
Leave a message below and we’ll get in touch with you shortly.

Moe ZSS

D Form Civil where awarded the FRP Package by client FRR Cinel as part of the REFCL upgrade of Moe Zone Substation. The team undertook the scope consisting off FRP of all New Station Footings, Bored piers, detailed excavation, Switch room suspended slab and Insitu cable Duct works.

The upgrade of this substation was required as part of the government mandated bushfire risk mitigation programme. D Form Civil successfully delivered our scope of works on time with no safety or environmental incidents.

Get in touch
Leave a message below and we’ll get in touch with you shortly.

West Melbourne Terminal Station

The West Melbourne Terminal Station rebuild project involved the replacement of existing infrastructure. This facility is one of several high-voltage electricity terminal stations serving Melbourne’s CBD and inner suburbs.

D form Civil successfully assisted long standing client, Multiworks in delivering the full FRP works on time and within budget. Replacing the existing assets with new, more modern technology of GIS gas insulated switch gear allowing this infrastructure to be housed inside buildings. 

Get in touch
Leave a message below and we’ll get in touch with you shortly.