Victorian Big Battery

This project is one we have proudly completed for the Victorian Big Battery (VBB) 220kV/33kV Connection Substation. VBB is a 300MW Grid-Scale Battery Storage, which is a key part of the Victorian clean energy transition.

We recently completed the full Civil and Structural package for our very valued client Downer, which included:

– Bulk earthworks
– Conduits and drainage
– In-ground oily water storage tank
– Structural foundations
– Fencing
– New bay of foundations in existing terminal station

There were a couple of challenges that our team faced, namely unseasonable weather that caused delays at project commencement and Intricate coordination with other key contractors.

With challenges came some massive highlights. One team approach harnessed by D Form Civil and Downer allowing the project to be delivered successfully on time. We also had zero MTIs or LTIs, and the finish was of the highest quality.

Staging

Final Stage

Get in touch
Leave a message below and we’ll get in touch with you shortly.

Moggs Creek Bridge Replacement

D form Civil were engaged in a bridge replacement on the Great Ocean Road at Moggs Creek by our client, Maca Infrastructure. The new bridge project for the famous costal road is to ensure the road remains safe and accessible.

Our team were commissioned to complete the scope of full formwork, Reo and Pour Package (FRP) of the new bridge structure. The delivery of this project evolved into additional works, D Form Civil performed the completion of drainage pits, kerb, channel, and bridge façade including an ocean-side pedestrian pathway to improve safety for all users.

Extra care and consideration had been taking into the planning process and systems were continually reviewed throughout the stages of these works due to the COVID-19 Pandemic. The safety of all site personnel and the wider local community were at the forefront of the decision-making processes.

Get in touch
Leave a message below and we’ll get in touch with you shortly.

St Kilda Shakespeare Grove

D form Civil worked closely on the Shakespeare grove pier project with John Holland to deliver the FRP package.

This project involved the replacement of the main drain outlet and the construction of a viewing platform opposite Shakespeare Grove in St. Kilda. The project included the removal of the existing culverts, installing new culverts and creating a new walkway to a new viewing platform. D Form Civil’s Scope entailed:

  • Installation and sealing of 58 precast culverts.
  • Form, Reo and Pour of Topping slab on precast culverts.
  • Application of protective coating topping slab.
  • Reinstatement of concrete and asphalt footpaths.
  • Construction of stone-faced retaining wall.
Get in touch
Leave a message below and we’ll get in touch with you shortly.

Mt Hotham Alpine Gateway Carpark

Form, Reo & Pour Package associated with the construction of a new 2 level carpark:

  • 25 No. Column Pad Footings
  • 160lm of Strip Footings
  • 100lm of 4m High In-Situ Walls
  • 2000m2 Ground Slab
  • 1800m2 Topping Slab to Hollowcore Planks
Get in touch
Leave a message below and we’ll get in touch with you shortly.

Glenrowan Interpretive Centre

On the lookout for Ned Kelly! Having been engaged by Midson Construction Vic, D Form Civil delivered both the Civil and Concrete Package of works for the construction of the Ned Kelly Interpretive Centre located in the heart of Glenrowan. 

With a wonderful architectural design for the new building that helped bring history to life, D Form Civil completed the following works:

  • Excavation and preparation of ground beams and slab.
  • Form, Reo & Pour the ground beams and slab.
  • Construction of in-situ reinforced concrete suspended slab.
  • Construction of in-situ reinforced concrete circular access stairs.

The final delivery of the Centre is a testament to our clients, designers and the local council in delivering a legacy project for the community and tourists for decades to come.

Get in touch
Leave a message below and we’ll get in touch with you shortly.

Mt Higginbotham Water Tank

DForm Civil were engaged by Mount Hotham Alpine Resort (MHAR) to aid with construction of a new potable water storage tank facility on top of Mt Higginbotham. The new tank will supply the Mt Hotham Village along with the snowmaking system at the Big D Ski slopes. 

Our team was called in to complete the Form, Reo, and Pour (FRP) package for the new tank. This entailed:

  • The construction of a base slab
  • Circular formwork design for 21m Diameter Tank, 6m High
  • Installation and Sign off of formwork
  • Installation of reinforcement
  • Pouring walls in 2 separate pours
  • Landing of precast columns and panels for the roof
  • In-situ concrete conical roof section. 

With the aim of completing the project prior to the start of the 2024 ski season, our team opted to move forward with a prefabricated Peri formwork system for the radial wall sections. Working alongside the engineers at Peri, we were able to design a system that would reduce the number of concrete pours, which in turn, helped us speed up construction of the water tank.

Get in touch
Leave a message below and we’ll get in touch with you shortly.

Caulfield Racetrack Early Works

Our first project for Simpson Construction Company, this project entailed assisting in the construction of 2 Substations as part of the Caulfield Racetrack upgrade. 

The Scope of Works centred around the Formwork, Reinforcement and Concrete package to construct the East & West substations and below ground access ramps. The package incuded:

  • Ground Slabs with Cable Trenches
  • Approach Slabs
  • Suspended Roofs
  • In-situ Stairs
  • Vehicle Ramps & Kerbs

Having overcome some challenging ground conditions, the team delivered this portion’s function, to create the key utility required for the long-term plan for racetracks largest redevelopment plan.

Get in touch
Leave a message below and we’ll get in touch with you shortly.

Rushworth Bridge

D Form Civil were engaged by our client Bild Group to complete a bridge replacement project in regional Victoria. The project was to replace the existing bridge on the Rushworth-Girgarre Road, due to its age and size, with a larger more efficient bridge. The project consisted of demolishing the existing bridge while simultaneously constructing the new bridge in a timely manner to re-open that stretch of roadway.

The D Form Civil package comprised of the full formwork, Reo and Pour Package (FRP) of the new bridge structure. This entailed 2 bridge abutments, the bridge deck/kerb and diaphragm, the landing of the Super T beams, walkway construction with temporary handrail and 2 approach slabs. The team used the conventional formwork method for construction of the abutments which allowed for speedy construction and re-use for the deck/diaphragm pour. The team were faced with below zero temperatures during the construction of the deck and had to improvise by implementing thermal blankets to meet Vic Roads specification and deliver a high-quality finished product.

Get in touch
Leave a message below and we’ll get in touch with you shortly.

St Peters Apostle Primary School

D Form Civil were engaged in the new St Peter Apostle Primary school build located in Hoppers Crossing in Victoria by our client Midsons. The project was to deliver a new build on the grounds of the existing primary school to provide a larger learning centre for the ever growing population in the area.

The team were assigned with delivering the full civil and structural scope of works which included the formwork, reinforcement and concrete. The project scope included the completion of all the foundations, 2 floor slabs, 2 sets of in-situ concrete stairs, a lift shaft and 4 circular columns throughout the 500m2 building. 

Some challenges were encountered along the way including unfavourable ground conditions leading to the foundations of the building being modified to suit with some small design changes. The High quality seen in the finished product of the school is a testament to the ability and drive in all of the members of the D Form Civil team.

Get in touch
Leave a message below and we’ll get in touch with you shortly.

Hotham Fire Water Tank

Following on from a previous project, D Form Civil were services with the delivery of a new Fire Water Storage Tank to facilitate the new Alpine Gateway Carpark & Day Centre for Mt Hotham Resort Management.

Working within tight conditions, and through some severe weather conditions the work crew delivered the in-situ tank including:

• Base Slab
• Formwork Design
• In-Situ walls
• External in-situ pits.

D Form Civil were proud to be able to deliver this final portion of works to allow the successful opening of the carpark.

Get in touch
Leave a message below and we’ll get in touch with you shortly.